The traditional method of obtaining groundwater in rural areas of the developing world, and still the most common, is by means of hand-dug wells. However, because they are dug by hand their use is restricted to suitable types of ground, such as clays, sands, gravels and mixed soils where only small boulders are encountered. Some communities use the skill and knowledge of local well-diggers, but often the excavation is carried out, under supervision, by the villagers themselves. The volume of the water in the well below the standing water table acts as a reservoir, which can meet demands on it during the day and should replenish itself during periods when there is no abstraction. DimensionsDepths of hand-dug wells range from shallow wells, about five meters deep, to deep wells over 20 meters deep. Wells with depths of over 30 meters are sometimes constructed to exploit a known aquifer. It is impractical to excavate a well which is less than a meter in diameter; an excavation of about 1.5 meters in diameter provides adequate working space for the diggers and will allow a final internal diameter of about 1.2 meters after the well has been lined. Digging with the sides of the excavation supported
There are several methods of supporting the sides of the excavation while digging proceeds:
Digging with the sides of the excavation unsupportedIn stable ground, wells are often excavated down to water level without a lining, and are lined with in situ concrete, or with pre-cast concrete rings, from this level upwards. Wells safely dug during the dry season may become unstable when the water level rises in the wet season and therefore must be lined before this occurs to prevent a collapse. Although in firm stable ground unlined wells may be safely excavated and may give long service in operation, it is prudent, and in most cases essential, to provide a permanent supporting lining which will support the sides of the excavation and prevent them from collapsing; suitable lining materials are concrete, reinforced concrete, ferrocement, masonry, brickwork, etc. Excavation below the water levelRegardless of which method has been used to excavate the well to the water table, excavation below this level should never be attempted until the sides of the excavation have received the support of their permanent lining, from water table to ground level. Excavation below the water table should be carried out within pre-cast concrete caisson rings of a smaller diameter than the rest of the well. The initial caisson ring is provided with a cutting edge and additional rings are placed on top of it; as the material within is excavated, the rings sink progressively under their own weight.
Alternative ways of lining a well Although WaterAid favors the use of pre-cast concrete rings, which become the permanent lining of the well after being sunk progressively as excavation proceeds within them, many other materials have been used successfully.
Completion After construction of the well shaft has been completed, the bottom is plugged with gravel. This helps to prevent silty material from clay soils, or fines from sandy materials, being drawn into the well. Any annular space between the pre-cast caisson well rings and the side of the excavation should also be filled with gravel; such filling behind the rings which are below the water helps to increase water storage and to prevent the passage of fine silts and sands into the well. The space behind the top three meters, or so, of the well rings should be backfilled to ground level with puddled clay, or concrete, and the well rings should project about one meter above a concrete apron. This apron provides a sanitary seal to prevent polluted surface water seeping into the well and should slope away from it and drain into a channel which discharges into a soakaway. AbstractionIt is desirable for the well to have a concrete cover slab, to reduce the possibility of contamination. Water is abstracted by means of either a bucket and windlass above an access hole, or a hand-pump, depending upon the yield of water available and the ability of the benefiting community to pay for ongoing maintenance for the handpump, spare parts, etc. A hand-dug well fitted with a hand-pump can serve the needs of about 300 people. The following diagrams show a typical layout for the well head of a well with a hand-operated windlass:
Download the full set of technology notes ( References:Hand Dug-Wells and their Construction S.B.Watt and W.E.Wood - IT Publications, 1985 WaterAid's Health and Safety Policy July 2000
|
||||||||||||
|
|